The Federal Reserve has, for the first time, examined how the AI buildout is being financed, and the findings should concern anyone who believes capital works best when risk is visible. The Fed's November Financial Stability Report adds a new section, 'Leverage in the Data Center Buildout.' None of its five previous editions, going back to 2024, had one.
The numbers come first. The report counts more than $1 trillion in leases that are signed but have not yet started, plus more than $2 trillion in take-or-pay contracts and residual value guarantees at Amazon, Alphabet, Broadcom, Meta, Microsoft, Nvidia and Oracle. Fed Governor Michael Barr, citing the report in a speech in Milan, put the 'potential maximum nominal value' of those obligations above $3 trillion. He said the seven largest AI firms' on-balance-sheet debt 'is expected to exceed $800 billion before year's end.' The Fed itself notes that the off-balance-sheet figures are undiscounted and 'not directly comparable' with debt, which is precisely the problem: the figures are real, but they are hard to compare and easy to overlook.
The report says these arrangements let companies with strong credit support weaker-credit projects 'without having an immediate, direct effect on the balance sheets' of the big firms. Data-center developers use the leases to finance construction, and the riskier slices of the resulting debt are held by high-yield bond funds, life insurers, business development companies and other private debt vehicles. According to the Fed, the largest U.S. bank holding companies have 'close to $1 trillion of exposure' to large technology firms, data-center developers, AI-related special purpose entities, private credit vehicles and utilities. Barr warned that the opacity 'can exacerbate selloffs when investor sentiment shifts, as it is hard to know where risk resides.'
Debt issuance tied to advanced computing rose to more than $680 billion by October, about five times the $130 billion issued in all of 2023. Advanced computing's share of nonfinancial investment-grade corporate debt issuance climbed from less than 6% in 2023 to about 31% this year. Market participants are noticing. In a Fed survey of 23 contacts at broker-dealers, banks, investment funds and advisory firms conducted in September and October, 87% named AI as a salient risk to the financial system, up from 50% in the May survey.
The guarantees are not abstractions. Nvidia agreed in August to residual value guarantees with SB Energy, the landlord for an AI campus in Pike County, Ohio, where an OpenAI affiliate will be the tenant. Nvidia's total obligation is 'cumulatively capped at $105 billion' for the initial commitment, and OpenAI has agreed to reimburse Nvidia for anything it pays. Nvidia's latest quarterly filing also lists $3.5 billion in guarantees on AI cloud partners' data center leases as of July 26. Barr said such guarantees 'represent the degree to which hyperscalers and GPU producers might absorb losses' if borrowers default.
The Fed's report reflects data through October 28. Since then, Nvidia CEO Jensen Huang resigned on November 12, and CFO Colette Kress became interim CEO. Nvidia reports third-quarter results after the close today.
The market has already voted on risk before the regulators finished counting it. Capital rewards clear rules, and clear rules mean knowing who owns the downside. Right now, that answer is buried in leases, guarantees and private vehicles that few investors can fully price. The Fed deserves credit for putting the figures on the record. Taxpayers and shareholders should ask why an industry this leveraged was able to grow this large before anyone asked the question.