The tech industry is built for speed. The power grid is not.
That collision now sits at the center of the AI buildout. Citigroup projects Big Tech will spend more than $2.8 trillion on AI infrastructure through 2029. A Brookings study puts U.S. investment at $10.3 trillion between 2025 and 2032.
The grid cannot keep pace. Since 2000, power consumed by data centers has risen an average of 19% a year. U.S. grid capacity has expanded just 2% annually, according to an analysis by insurance broker Howden. Data center demand is growing roughly ten times faster than the system built to supply it.
The numbers are already large. Data centers took about 5% of U.S. grid capacity in 2025. Lawrence Berkeley National Laboratory projects they could use as much as 12% of U.S. electricity by 2028, about six times their 1.9% share in 2018.
Rob Gramlich, president of consulting firm Grid Strategies, described a real 'mismatch in timing.' Grid expansion depends on thousands of interconnected parts. That requires 'deliberate study and planning' that can take years. He also noted that utilities 'got out of practice on building new infrastructure' after roughly 25 years of little growth in power demand.
Delays are the expected outcome. Kathryn Burke, who leads U.S. specialty energy and power growth at insurance firm Marsh, told Fortune she expects 50% to 60% of data center projects to slip beyond the one-to-two-year timelines developers are counting on.
The politics have shifted too. On Nov. 3, voters rejected data center development in 40 of 41 local ballot measures. Opposition runs deepest among the young. A University of Pennsylvania Annenberg Public Policy Center survey found 70% of adults under 30 oppose new data centers in their area, compared with 61% of all adults.
The fears have a basis. Northern Virginia hosts the world's largest concentration of data centers. As of 2025, commercial energy demand exceeds residential demand in 23 states and Washington, D.C.
A study in Nature Energy by Cornell University researchers Cheng Feng and Fengqi You found that data centers raised wholesale power prices unevenly. In California's southern Bay Area, the researchers estimated a lift of nearly 20% in 2025. Around Dallas-Fort Worth, the increase approached 17%. Across the four grids studied, data centers paid only 38% of the infrastructure costs tied to their growth: $3.12 billion of an $8.25 billion bill.
Wholesale prices make up only about 30% to 50% of a household bill. Experts still expect residential customers to cover part of the AI buildout. The Cornell researchers found the costs fall hardest on lower-income and rural households.
Tech companies are responding by generating their own power, a model the industry calls 'bring your own power.' Delaware became the first state to legislatively enact a 'bring your own generation' policy. It requires large energy users, including data centers, to produce or secure 100% of the power they use, within 10 years of starting operations.
President Donald Trump's Ratepayer Protection Pledge asks signers to 'build, bring, or buy' the new-generation resources and electricity they need. Amazon, Google, Meta, Microsoft, OpenAI, Oracle and xAI signed in March, and more than 200 utilities, cooperatives, developers and Republican governors have since joined. The pledge is not binding.
The market has already signaled the answer. When a cost is real, the party that causes it should carry it. The Cornell figures show data centers paid barely more than a third of the infrastructure bill their growth created. The rest landed on other ratepayers, many of them the households least able to absorb it.
Capital will flow to power where the rules are clear and the costs are priced honestly. Bring-your-own-power rules push that discipline onto the companies that create the demand. A grid that grows 2% a year cannot be fixed by pretending demand will wait. It can only be fixed by making those who draw the power pay for the capacity it requires.